Posted on: May 2, 2019

End of the Line!

IMG_0389

M&F installed the HC ramp at the school entrance yesterday, which means that concrete work is now complete for this project.  All that remains is a small amount of backfilling and seeding.

Westminster Sidewalk
Posted on: April 25, 2019

Week of 4/22/19

The contractor is nearing the home stretch of the sidewalk portion of the job.  They are now working on the area between Winsor Court and the school entrance.  This is in spite of the fact that they did not start pouring concrete until A...

Read on...