2019 Water Main Improvements

Posted on: June 12, 2019

Week of 6/10/19

The water line tie-ins have been completed along N. Shenandoah Ave. and the contractor has saw cut the pavement along W. 14th Street.  This week they will begin digging a trench along 14th St. and installing a new 10" water main.  This work will take place during the day and will take approximately three weeks to complete.  Please use caution when driving on 14th St. and be alert for construction workers and lane closures.