Section 175-109 TEMPORARY CONSTRUCTION TRAILERS.
A.
Zoning permits for temporary trailers may be issued by the
Zoning Administrator in any zoning district for construction purposes
only.
Temporary trailers may not be used for residential purposes or sales
offices.
All permits for temporary construction trailers shall be
subject to
the following conditions:
1.
The Zoning Administrator shall review and
approve or deny all requests for temporary construction trailer
permits.
In assessing a request for a temporary construction trailer permit, the
Zoning
Administrator shall consider the necessity for such temporary
construction
trailer, its location and its effects on the surrounding neighborhood
and/or
adjoining property owners and may require terms and conditions on the
location
and placement, type and number of trailers, screening and such
other
reasonable conditions as the Zoning Administrator shall deem necessary.
2.
The location of temporary construction trailers
on a specific site shall be necessary for the purpose of a construction
office
or storage.
3.
The request for a
temporary construction trailer permit shall be filed by the contractor,
landowner or State Department of Highways and Transportation as being
essential
to the construction activity.
4.
A minimum area of two thousand (2,000)
square feet shall be provided for each temporary construction trailer
space.
5.
Each temporary construction trailer shall
have a minimum of two (2) off-street parking spaces in addition to
other
parking spaces required by this chapter for other activities.
6.
All sanitary
facilities must conform to State Health Department trailer camp
sanitation
requirements.
B.
The maximum period allowable for the placement of a
temporary construction
trailer shall be six (6) months or until completion of the project,
whichever
is shorter. Applications for renewal for a successive six-month periods
may be
submitted if additional time is required to complete the project.
However,
each renewal application must be filed at least thirty (30) days prior
to the
expiration of the original temporary construction trailer permit.
C.
The Zoning Administrator, in granting a temporary
construction trailer permit, may require the posting of a bond to
insure
that the temporary construction trailer will be removed and the site
left in
good order at the expiration of the permit.
D.
The Zoning Administrator may establish such additional
requirements and conditions as may be in the best interests of the
town.