Chapter 148 SUBDIVISION AND LAND DEVELOPMENT. (updated 7-28-08)
Section 148-24 INSTALLATION OF IMPROVEMENTS.
A. All
required on-site and off-site improvements
shall be installed by the applicant at his cost and shall be dedicated
to the
Town of Front Royal, unless reserved for private ownership and
maintenance, as
provided herein. All installation of public improvements shall be
carried out
under town inspection. The subdivider or developer shall submit the
necessary
construction details, shop drawings and cut and fill construction
sheets for
approval by the town and shall secure all required permits in advance
of
construction. All utilities and facilities shall be installed in
accordance with
the Town of Front Royal, Virginia, Standards and Specifications, as
periodically amended.
B. All
required improvements shall be installed
within eleven (11) months of final plat approval or such other period
as may be
approved by the Town Council. Upon written application, extensions of
time to
complete required improvements may be approved by the Front Royal Town
Council,
which may provide additional bonding requirements as a condition of any
extension granted.
C.
Upon completion of the construction and installation of
required improvements and as a condition of the acceptance thereof by
the Town
and the release of performance bonds or other securities, the
subdivider or
developer shall provide the Town with as-built plans showing the
locations and
elevations or invert elevations of the required improvements.
(Ord.
No. 5-04 Added (C)